Y'all City Hall

What Austin City Council is voting on, in plain English, with a link to every record.

← Thursday, March 12, 2026

Item 16 Passed 11-0

Item 16 — Thursday, March 12, 2026

Official votes

Current official agenda wording

Authorize an amendment to the construction contract for the Walnut Creek Wastewater Treatment Plant Expansion to 100 Million Gallons per Day Project with MWH Constructors Inc., to increase the contingency by $600,000,000, for a revised total contract amount not to exceed $1,500,000,000. Funding: $600,000,000 is available in the Capital Budget of Austin Water.

The roll call

City of Austin headshots stay on the council page. The City's terms allow personal use of austintexas.gov images, so this roll call shows initials.

Approved on Consent 11-0

Member records (11)